Local, State, and Federal Agency approvals research aimed at discovering potential environmental impacts has dominated the university's work on the LSC Project since 1994. This research and the applications outlined in the following chart include

  • twelve major permits or reviews, as required by local, state, and federal agencies and multiple other non-discretionary permits or approvals
     
  • New York State Environmental Quality Review (SEQR)
     
  • Draft Environmental Impact Statement (dEIS)

 
PERMIT/APPROVAL REGULATORY AUTHORITY ACTION(S)
Protection of Waters Joint Permit (Terrestrial Construction) NYSDEC; USACOE " Stream bank/bed disturbances
" Placement of fill in stream (Pleasant Grove Stream)
" Water-quality certification for construction in navigable waters
Protection of Waters Joint Permit (Lake Construction) NYSDEC; USACOE

" Excavation of lake shore
" Structures in lake
" Excavation of lake sediments
" Placement of fill in lake
" Water-quality certification for construction in navigable waters

General Storm Water Discharge Permit No. GP-93-06/ Notice of Intent, (For Construction Activities) NYSDEC Lake Source Cooling construction activities
SPDES Permit (Industrial) NYSDEC Facility operation
Underwater Land Easement NYS OGS Installation, operation, and maintenance of intake and outfall
Water Withdrawal Registration NYSDEC Water use in Great Lakes watershed
Wild, Scenic, Recreational River Crossing Permit City of Ithaca Pipeline crossing above Fall Creek (under Lake Street bridge between existing girders)
Cultural Resource Survey NYS Office of Parks/Recreation Project construction
Highway Crossing Permit NYSDOT Underground highway crossings by terrestrial pipeline
Street Opening Permit City of Ithaca
Department of Public Works
Construction beneath city streets and in rights-of-way
City Street Easement;
Infrastructure Replacement
City of Ithaca
Common Council
Operation of chilled-water lines beneath city streets; infrastructure replacement associated with piping installation.
Site Plan Approval Town of Ithaca
Town Board and Planning Board
Development of land within town
Subdivision Approval Town of Ithaca
Planning Board
Subdivision of land within town
Zoning Change Town of Ithaca
Town Board
Creation of Special Land Use District for heat-exchange facility
Building Permits Town of Ithaca Construction of heat-exchange facility
Property Easement Cayuga Heights
Village Board
Terrestrial pipeline construction and operation within village property
Property Easement ICSD Board Terrestrial pipeline construction and operation within ICSD property
ICSD Ithaca City School District
NYSDEC New York State Department of Environmental Conservation
NYSDOT New York State Department of Transportation
NYS OGS New York State Office of General Services
SPDES State Pollutant Discharge Elimination System
USACOE U.S. Army Corps of Engineers