Case Study #5: Biotechnology Building

 

 

 

 

Scope of Work

·        Recommissioned the existing mechanical and control systems to optimize overall system performance.

·        Replaced the existing two-position constant volume air system with a high performance variable air volume system in 90 labs to reduce the unnecessarily high air change rates.

·        Installed PIR occupancy sensors and replaced the existing pneumatic controls with electronic controls in 200 labs to enable occupied and unoccupied modes of operation.

·        Installed PIR occupancy sensors in the corridors to reduce lighting levels in public space when the spaces are unoccupied.

 

Project Completed

 

Project Cost

 

Energy Savings

 

Simple Payback